PrintBranch
PB-2401-0143
Rigid Box
Delay Risk
In Production

Premium Rigid Box (Speaker)

Atlas Audio · created 29-04-26

1 Day Left
Priya (Sales):Customer requested matte finish lamination — non-negotiable.
Ordered Qty
800pcs
Progress
64%
Projected Dispatch
2026-05-22
vs promised 2026-05-18
Raw Material
Awaiting RM
Auto from process flow
Total Order Time
22d 19h
Planned 11d · +11d slip
Operational Risk Indicators
Delay Risk
Procurement
Vendor Dependency
Raw Material
QC
Dispatch

Process Management

Dynamic production flow · add, reorder, assign · capture logistics inline

Printing
Completed
Shree Offset · planned 2d · actual 2d
Lamination
Completed
Shree Offset · planned 1d · actual 1d
Foiling
Completed
Foil Studio · planned 2d · actual 2d
Die Cutting
Completed
Vista Pack · planned 1d · actual 1d
Assembly
In Progress
Vista Pack · planned 3d · actual 0d
QC
Pending
Internal · planned 1d · actual 0d
Dispatch
Pending
Internal · planned 1d · actual 0d