Corrugated Shipper 5-ply
Brewroom · created 05-05-26
Due Today
Priya (Sales):Customer requested matte finish lamination — non-negotiable.
Ordered Qty
8,000pcs
Progress
30%
Projected Dispatch
2026-05-25
vs promised 2026-05-17
Raw Material
Awaiting RM
Auto from process flow
Total Order Time
16d 19h
Planned 8d · +8d slip
Operational Risk Indicators
Delay Risk
Procurement
Vendor Dependency
Raw Material
QC
Dispatch
Process Management
Dynamic production flow · add, reorder, assign · capture logistics inline
Printing
Completed
+1d slip
Shree Offset · planned 2d · actual 3d
Die Cutting
Delayed
Pack Hub · planned 2d · actual 0d
Pasting
Pending
Pack Hub · planned 2d · actual 0d
QC
Pending
Internal · planned 1d · actual 0d
Dispatch
Pending
Internal · planned 1d · actual 0d