PrintBranch
PB-2401-0148
Monocarton
Delay Risk
In Production

Tea Monocarton 250g

Forest & Co. · created 09-05-26

2 Days Left
Priya (Sales):Customer requested matte finish lamination — non-negotiable.
Ordered Qty
5,000pcs
Progress
21%
Projected Dispatch
2026-05-23
vs promised 2026-05-19
Raw Material
Awaiting RM
Auto from process flow
Total Order Time
12d 19h
Planned 8d · +4d slip
Operational Risk Indicators
Delay Risk
Procurement
Vendor Dependency
Raw Material
QC
Dispatch

Process Management

Dynamic production flow · add, reorder, assign · capture logistics inline

Printing
Completed
Shree Offset · planned 2d · actual 2d
Lamination
In Progress
Shree Offset · planned 1d · actual 0d
UV
Pending
Foil Studio · planned 1d · actual 0d
Die Cutting
Pending
Pack Hub · planned 1d · actual 0d
Pasting
Pending
Pack Hub · planned 1d · actual 0d
QC
Pending
Internal · planned 1d · actual 0d
Dispatch
Pending
Internal · planned 1d · actual 0d